At times, teams may decide to select certain working days of week for a project. To accommodate such situations Yodiz gives teams leverage of selecting any days of the week as working days for a project. To set the working days of the week.
  1. Log in to Yodiz.
  2. Click on
    Administration
    from upper right menu. admin
  3. Under the Projects setting, select
    View All Projects
    . view all
  4. Click the Settings button for the project in which you want to edit work days. projsetting
  5. Select the Settings tab, and tick the work days that you want to keep. work days
  6. On the Project setting check the working days of the project. In following picture only 4 days are selected as working days.